Work centres
Set up the places work is done - a line, a machine, a bench - with what an hour there costs and the account that cost is absorbed into.
A work centre is where work is done: an assembly line, a machine, a packing bench. It carries a cost per hour covering the labour, machine time and overhead of an hour there. Routes use work centres for each step, and that cost is absorbed into what is made.
The cost of labour and machines is already in your books as expenses: salaries, rent, depreciation. When goods are made, the work centre's share of it is moved out of those costs and into the value of the stock, by crediting the work centre's absorption account and debiting Inventory.
Before you start
- An account to absorb the cost into exists in the chart of accounts, usually a production overheads absorbed account. Any posting account can be chosen.
- You hold the Accountant role or higher.
Create a work centre
- Go to Production › Work centres and choose New work centre.
- Enter a Code and a Name.
- Enter the Cost per hour, in the base currency.
- Choose the Absorb into account. It is required when there is a cost per hour.
- Choose Create.
Fields
| Field | What to enter |
|---|---|
| Code | Up to 20 characters, saved in capitals. Must be unique. |
| Name | What the work centre is called. |
| Cost per hour | Labour, machine and overhead for an hour here, in the base currency, to two decimals. Leave at 0 for a step that takes time but carries no cost. |
| Absorb into account | Credited with the cost of the work as goods are made. Required when Cost per hour is more than zero. |
| In use | Untick to stop offering it on new routes. |
What it posts
Nothing. The work centre is used when an assembly order posts. For example, a route step at a work centre costing AED 120.00 an hour that takes 30 minutes in all posts:
| Account | Debit | Credit |
|---|---|---|
| Inventory | 60.00 | |
| Production overheads absorbed (the work centre's account) | 60.00 |
Correct or change it
You can change a work centre at any time. A new cost per hour applies to costing and to assembly orders posted from then on; assemblies already posted keep the cost they were made at. Work centres cannot be deleted; untick In use instead.
Related articles
- RoutesList the steps an item goes through to be made, each at a work centre, with setup time per batch and run time per unit.
- Production costingSee what it costs to make any quantity of an item - each component at what it is held at, plus the time at each work centre - before you make it.
- Post an assembly orderMake goods from a bill of materials - the components leave stock, the finished item comes in at their cost plus the work, and the work is posted.
- Chart of accountsReview the UAE chart your company starts with, add accounts and headings, and understand which accounts the system posts to by itself.