Project costs and revenue

Tag invoice, bill, voucher and journal lines to a project, and see exactly which posted amounts count as its revenue and its cost.

A project earns and spends money only through the ledger. Nothing is entered on the project itself: you choose the project on the documents you already post, and the project reads the journal lines that carry it.

Where you choose the project

Where How
Sales and purchase documents (quotations, orders, invoices, credit notes) The Project field at the top defaults onto every line. Each line can be changed, so one invoice can serve several projects.
A Project line on a sales or purchase document Set the line Type to Project and choose the project. The line posts to the account you choose on it; if you leave that empty, it posts to the first income account (on a sale) or the first expense account (on a purchase) in your chart, by code.
Receipts, payments and other vouchers The Project field on the voucher.
Journal entries The project on each journal line. Use this to charge salaries, overheads or accruals to a project.

The field shows only when the company has at least one active project. If your company has made the project dimension mandatory, the form marks it with an asterisk and will not save without it. See Dimensions and cost centres.

Note

Invoices raised from service work orders and contracts, and rent invoices from the rental schedule, are created without a project. Set the project on the draft before you post it if you want it counted.

What counts

The project's figures are worked out from every posted journal line tagged with it, in your base currency:

Figure Made of
Revenue Credits less debits on income accounts.
Cost Debits less credits on expense accounts.
Profit Revenue less cost. The margin is profit as a percentage of revenue.

Lines on balance sheet accounts (receivables, payables, VAT, bank, inventory) can carry the project and show in its Latest postings and in the project ledger, but they are not revenue or cost.

Worked example

Project P-014, a shop fit-out, budgeted revenue AED 120,000.00 and budgeted cost AED 90,000.00.

A sales invoice for AED 40,000.00 plus 5% VAT, tagged P-014, posts:

Account Debit Credit Counts as
Accounts receivable 42,000.00 Nothing (balance sheet)
Contract income 40,000.00 Revenue 40,000.00
VAT output 2,000.00 Nothing (balance sheet)

A purchase invoice from a joinery subcontractor for AED 25,000.00 plus 5% VAT, tagged P-014, posts:

Account Debit Credit Counts as
Subcontractor costs 25,000.00 Cost 25,000.00
VAT input 1,250.00 Nothing
Accounts payable 26,250.00 Nothing

The project page then shows revenue AED 40,000.00 (33% of budget), cost AED 25,000.00 (28% of budget) and profit AED 15,000.00, a 37.5% margin.

Goods sold from stock on a tagged sales invoice also post their cost of sales with the project, so the cost of the goods counts against the project too.

Correcting a project's figures

Posted entries are never edited. If a line went to the wrong project:

  • A document: reverse it or issue a credit note, then post it again with the right project.
  • To move an amount between projects: post a journal entry that credits the expense or income account on the wrong project and debits it on the right one. The account balance does not change; only the project tags do.

Related articles

Was this page helpful?

Tell us what was missing or wrong, with the page address, and we will fix the article.